Sunter Lake Dam Targeted to Finish Two Weeks Ahead

North Jakarta Water Resources (SDA) Sub-dept. targets to complete dam construction on south side of Sunter Lake on February 20. For information, this work has been started since last week.

We start it from last week and target to complete it on February 20

North Jakarta SDA Sub-dept. Head, Santo conveyed, his side constructs dam along 90 meters on west side of lake.

Sunter Lake Arrangement Reaches 30 Percent

"We start it from last week and target to complete it on February 20," he affirmed, Wednesday (2/7).

Not only to prevent landslide, but this dam with around 2.5 meters wide is also prepared to support tourism.

"We use river stone for its material. We give sloof in each 20 meters for citizen who wants to sit or for fishing spot," he explained.

Linked News
Popular News indeks
  1. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1684 personAldi Geri Lumban Tobing
  2. Ciliwung River Normalization Accelerated, Pramono Ensures Land Acquisition Without Intermediaries

    access_time10-07-2026 remove_red_eye1473 personDessy Suciati
  3. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye1332 personFolmer
  4. Pramono will Take Firm Action Against Individuals Involved in Extortion

    access_time13-07-2026 remove_red_eye1111 personDessy Suciati
  5. The Pegangsaan Dua-Manggarai LRT Project Reaches 95 Percent Completion

    access_time14-07-2026 remove_red_eye803 personDessy Suciati